A single construction project is undertaken by a multitude of firms comprised of a prime contractor and many subcontractors. Generally, these organizations are assembled only for the period of the construction project. The success of the project depends largely on whether subcontractor organizations can be properly engaged and managed. The general contractor has the right to define the work scope for each component of the construction project and to assign the subcontractor to carry out each subtask. Therefore, it is very important for the general contractor to develop a good subcontractor team based on the specific characteristics of each project. In this paper, we present a new concept of a sub-package problem by focusing on its management time and cost. Also, we formulate the sub-package problem as a mathematical programming model through which we demonstrate some numerical results.
寄稿の翻訳タイトルOptimization of Sub-package Problem in Building Construction Project: Proposal of Sub-package Support System
本文言語日本語
ページ(範囲)9-28
ページ数20
ジャーナル日本応用数理学会論文誌
12
1
DOI
出版ステータス出版済み - 2002

フィンガープリント

「建築プロジェクトにおける工事編成最適化: 工事編成支援システムの提案」の研究トピックを掘り下げます。これらがまとまってユニークなフィンガープリントを構成します。

引用スタイル